The "Bar" has been Risen - Toppan-Merrill - Sartell, MN

October 29, 2019
Structural steel and the roof bar joists are being set for the warehouse addition at Toppan-Merrill.  Steel work will continue next, and contractors will then begin to start the install of the roof system to make the addition weather tight.
 
Tags: Private / Other

Framing is Underway! - Toppan-Merrill - Sartell, MN

October 28, 2019
Steel stud framing and sheathing is under way at the exterior of the office addition for the Toppan-Merrill project.  Concrete curb and gutter onsite has been completed, and paving will begin this week.  
 
Tags: Private / Other

Rain, Rain, Stay Away! - Toppan- Merrill - Sartell, MN

October 25, 2019
Crews are working diligently to complete the roof system at Toppan-Merrils' office addition. In preparation of pouring the concrete floor slab in the upcoming weeks, they are hoping to dodge any unpredicatable weather in the forecast. 
 
Tags: Private / Other

Getting to know St. Cloud Rotaract Club-Sauk Rapids & Sartell Rotary

October 18, 2019
The Sauk Rapids and Sartell Great River Rotary Club hosted the latest gathering at the Red Carpet Martini Lounge where the Saint Cloud Rotaract Club was being highlighted. GLTA's- Steve Paasch took some time to introduce himself to the people behind the Saint Cloud Rotaract Club and other member organizations that were present. Read more about the Saint Cloud Rotaract Club from a previous WJON article here. 
Tags: Private / Other

Paramount Center For the Arts - St. Cloud, MN

October 15, 2019
GLTArchitects is a proud sponsor of St. Clouds' Paramount Center for the Arts.
"The mission of the Paramount Center for the Arts is to provide opportunities for artistic production, creative exploration, arts education and the enjoyment of arts and entertainment."  Please see the 2019-2020 Season- Fall/Winter Program here.   
Tags: Private / Other

Structural Steel System is Standing Tall! - Toppan-Merrill - Sartell, MN

October 11, 2019
Under slab utilities and piping are now complete at the office addition for Toppan-Merrill.  Crews are working on setting the structural steel system as well as the roof joist/decking system in between incliment weather conditions.  The contractors are operating towards pouring the concrete floor at the office addition as soon as the roof decking is in place, and crossing our fingers the weather cooperates!
 
Tags: Private / Other

It's Time for PreCast!! Toppan-Merrill - Sartell, MN

October 08, 2019
Precast Concrete Wall Panels continue to be set at the warehouse addition for the Toppan-Merrill project.  Crews are working around the addition to finish at the east wall and the side containing the shipping/receiving overhead door openings.  Structural steel system and the roof joist/decking system are the next steps in place after the precast wall panels are complete later this week.
 
Tags: Private / Other

Autumn Moon - Paramount Center for the Arts Annual Fundraiser Exceeds Expectations! - St. Cloud, MN

September 30, 2019
St. Cloud's Paramount Center for the Arts Annual Fundraiser Exceeded their fundraising goal of reaching more than $59,000, which is a historic high for the program. GLTArchitects is happy to help sponsor this program which "supports the Paramount's mission to provide opportunities for artistic production, creative exploration, arts education and the enjoyment of arts and entertainment. Monies rasied will fuel the wide range of Paramounts programs."
Tags: Private / Other

Toppan Merrill- onto The Rough-Grade! - Sartell, MN

September 25, 2019
Excavation continues near the office addition at Toppan-Merrill.  The excavating contractor has rough graded the site, and now is working to remove excess soils offsite.
 
Tags: Private / Other

Toppan Merrill- It's time for Foundation & Footings! - Sartell, MN

September 03, 2019
Construction on site slowed with recent weather, but not before foundation and footings had been poured at the office warehouse.  The work for placing under slab plumbing and preparing to pour concrete floor slab at the office addition to continue when conditions improve.
 
Tags: Private / Other