A Typical
Time-frame for Project-Planning
This time-frame
is typical of many design and building projects.
Your experience will certainly vary a bit from this,
but the message is clear: Start planning now for where
you want to be in the future!
Start
to 3 Months: Architect hired or Programming/Master
Planning
Months
4-6: Work
required for moratorium exceptions submittal (applies
only to Licensed Skilled Nursing Facilities applying
for the moratorium exceptions process in Minnesota).
Schematic Design process.
Months
7-10: Waiting period for moratorium exceptions
selection process (applies only to Licensed Skilled
Nursing Facilities applying for the moratorium exceptions
process in Minnesota).
Months
11-16: Design
Development Construction Documents
Month
17: Bidding
Months
18-29: Construction
|