October 27, 2014
The Sartell-St. Stephen School District was facing overcrowding in their middle school and GLTArchitects assisted them in researching options for additional classroom space.  The new addition, featured on the right side of the photo, was designed to blend in with an existing classroom addition and includes three classrooms to the south end of the school (3,850 s.f.).  The scope of work also included code upgrades to the existing school.  The project was on a very tight timeline.  Planning with the school district was done in March, construction documents were completed in April, bidding was done in May, and construction was completed over the summer to allow the new classrooms to be ready for the start of school, fall 2014.